Your customer has a main office that houses 450 employees and a call center that houses 120 employees. The main office and the call center are connected by a 100-megabits per second (Mbps) wide area network (WAN) link. The call center uses a Private Branch Exchange (PBX) that has 150 incoming lines.
Your customer plans to deploy a Lync infrastructure for atl employees.
You collect network information and start building a Lync usage model.
You need to identify the deliverables that must be achieved after the Lync usage modeling phase is completed. Which two deliverables should you achieve? (Each correct answer presents part of the solution. Choose two.)


A. Quality of Service (QoS) configuration
B. calculation of user-generated Lync traffic
C. calculation of server-to-server generated Lync traffic
D. calls simulation over the WAN link
E. RTC traffic estimation over the WAN link

Answer: AC                                                             Passleader 74-335 Practice Test